  1. BurningSky is offline resortX Top Investigator
    Join Date
    Jul 2023
    Posts
    245
    Huge Manchester Therme water resort update issued as costs rise to £400million
    Bosses have an issued an update to explain where they're up to on creating the massive 28-acre wellness resort next to the Trafford Centre
    Now, bosses have issued a new update on where things are at with the development. They say the "first major construction phase" will begin "later this year" after a lead construction group is appointed this week.





    Source: https://www.manchestereveningnews.co.uk/whats-on/whats-on-news/huge-manchester-therme-water-resort-31070502?utm_term=Autofeed&utm_medium=Social&utm_source=Facebook#Echobox=1740573764






  2. BurningSky is offline resortX Top Investigator
    Join Date
    Jul 2023
    Posts
    245
    Photos show that work has finally begun on the £250m Therme Manchester resort next to the Trafford Centre




    Therme bosses have announced that the development has now officially started after securing the latest approval from Trafford Council to planning amendments on the site which had set back the initial works starting. The redesign of the resort shows a new look for the exterior, that boasts a series of domed glass roofs.
    Bosses say they are now on track with their "revised timeline" although a new planned opening date has not yet been confirmed. The building works are expected to take two and a half years which would push the opening into 2027.
    Source: https://www.manchestereveningnews.co.uk/whats-on/whats-on-news/work-finally-begins-build-huge-30118312

  3. MrFacipieri is offline Resort Investigator
    Join Date
    Aug 2019
    Posts
    4

  4. BurningSky is offline resortX Top Investigator
    Join Date
    Jul 2023
    Posts
    245
    Nothing happening but the land is clear.



  5. mrg
    mrg is offline resortX Top Investigator
    Join Date
    Mar 2016
    Posts
    1,173

  6. HunterX is offline resortX Top Investigator
    Join Date
    Aug 2022
    Posts
    229
    Trafford’s £75m surf park and leisure resort project is finally moving again


    Originally slated to arrive in 2023, planning permission for Modern Surf Manchester was granted back in September 2021 but due to problems with funding, the hugely ambitious project has been held up ever since, with the opening date pushed back to sometime in 2025.
    Modern Surf is part of a larger 20-year project to upgrade the TraffordCity complex, with around £2.6bn set aside for the huge investment and undertaking, with this set to be the first inland surfing destination in the North of England — and we’ve already had a spellbinding glimpse of what it’s going to look like.
    The wider regeneration of Trafford Park also includes a whopping £250m set aside for the highly-anticipated, Therme Manchester , which was first announced back in 2020 and will be a similarly unprecedented addition to the region and the North as a whole.
    Source: https://themanc.com/news/modern-surf-manchester-trafford-surf-park-leisure-resort-therme/

  7. ResortsAhoy is offline resortX Top Investigator
    Join Date
    Jul 2019
    Posts
    1,135

  8. HunterX is offline resortX Top Investigator
    Join Date
    Aug 2022
    Posts
    229


    Initial designs for the spa resort were a single building with zones and an undulating roofline, but Trafford Council has approved plans for a £250 million flowing pavilion-style concept.
    This new design for Therme Manchester features separate connected structures that are “immersed and enveloped in a natural landscape”, with a revised location for car parking and enhanced connectivity with public transport.
    Source: https://www.twinfm.com/article/planning-approved-for-the-uks-first-city-wellbeing-resort

  9. MarkEm is offline resortX Top Investigator
    Join Date
    Nov 2020
    Posts
    544
    A £250million plan to create a huge waterpark and wellbeing resort at the site of the former Events City at Trafford Park looks set for approval. The scheme to create a resort - known as ‘Therme’ - goes before Trafford’s planning and development management committee meeting on Thursday, September 14.
    Four objections to the plan have been submitted to the council. These include fears over increased traffic and its disruption to nearby businesses; submissions that the filter for turning into Mercury Way from Barton Dock Road is not large enough; that the car park should be sited where the Event City parking was originally located; and objections to the use of Mercury Way for parking with a drop-off point.
    They also say the development requires changes to ‘third party land, which will impact on operations and adjacent businesses’ and that the plans take ‘no consideration of significant numbers of pedestrians being channelled into an area with regular vehicle movements and 40ft trailers to the neighbouring warehouse building’. The objectors also alleged inaccuracies and inconsistencies in transport surveys and data.
    Source: https://www.manchestereveningnews.co.uk/whats-on/whats-on-news/greater-manchesters-250m-waterpark-wellbeing-27664143